No minimum is needed for cycling. The number of units follows from the availability a customer needs.

Hugh McDermott, CCO · Investor Q&A video · Sep 30, 2026

Watch the whole Performance and economics video (11 min)

The full answer

No minimum is needed for cycling. A unit can do staged or partial cycling on its own.

What sets the number of units is availability. Each unit is being designed for 95% availability, with the remaining hours of the year covering routine maintenance and a small amount of unplanned outage. A customer that needs higher availability adds units, so one can be offline while the site still meets its load. Systems are generally deployed in clusters sized to the customer's duty cycle and availability requirement.